Congregation
Beth Elohim
274 Garfield
Place
Construction
Work Schedule
05/26/2008
– 05/30/2008
| Location |
Time |
Impact |
| 8th
Ave – Façade
New brickwork and stonework.
|
7:30 am –
6:00 pm
|
Minimum noise, minimum dust |
| Garfield
Place – Façade
New brickwork and stone work
|
Monday (Memorial
Day – Schools are closed) |
Minimum noise, minimum dust |
| Light
Well
Waterproofing flashing installation
|
Monday (Memorial Day
– Schools are closed) |
Minimum noise, unpleasant
smell |
| South
Façade
Raking the mortar
|
7:30 am –
6:00 pm
|
Moderate noise,
moderate dust |
06/02/2008
– 06/07/2008
| Location |
Time |
Impact |
| Demolish
Slab at Library
Mobilization at library
|
FRIDAY, SATURDAY |
Moderate noise, moderate dust |
06/09/2008
– 06/13/2008
| Location |
Time |
Impact |
| Demolish
Slab at Library |
Monday
– Shavuot (no children) |
Heavy noise, heavy dust |
06/16/2008
– 06/20/2008
| Location |
Time |
Impact |
| Light
Well
Asbestos roof removal.
Vapor barrier installation.
(Scaffolding required in Ballroom. The Ballroom will not be usable until
June 20).
|
7:30 am –
6:00 pm
|
Heavy noise, moderate dust |
07/28/2008
– 08/2008
| Location |
Time |
Impact |
| Main roof
removal |
7:30 am –
6:00 pm
|
Heavy noise, moderate dust |
September
– October
| Location |
Time |
Impact |
Continuation
of main roof installation
Installation of 10 foot railings
on roof
Installation of 42 inch railings
on new parapets
Cladding of bulkhead roof
Pointing of brickwork
|
7:30 am –
6:00 pm
|
Minimum noise, minimum dust
Minimum noise, minimum dust
Minimum noise, minimum dust
Minimum noise, minimum dust
Minimum noise, minimum dust
|
January
– April 2009
| Location |
Time |
Impact |
| South
east corner
Upper roofs
|
7:30 am –
6:00 pm
|
Heavy noise, moderate dust |
|