|
Page 1 of 8 Update Memo of May 22nd
First, we all want to thank those parents that attended and
participated in the May 20 Town Hall meeting. We hope we were successful in openly
and directly addressing the concerns and questions that were raised.
We assembled a team of experts to be on hand to answer the questions
from the floor. They were Catherine Paplin, AIA (architect), Henry Sztabinski, (contractor),
Michael Parpounas (environmental engineer) and Rick Weisfeld (our newly-hired
project manager). Congregation president David Kasakove opened the meeting and
introduced the participants. Congregation Beth Elohim’s new executive
director, Paul Basista, presented a brief slide show indicating the history of
the project, the scope of work and how we’ve addressed parent concerns to
date. Feedback from the audience was positive – parents expressed they
felt the Congregation was taking their concerns seriously and that it was
making good faith efforts to address them during the construction phase. We’ve
updated the Frequently Asked Questions to capture these questions.
Considering the deadline for school registration is June 1, the
question about what work will be done in September was an important one. While
we still don’t have a specific schedule, we do have a general
understanding of what the contractor plans for September and October. This is
reflected in the updated Construction
Schedule.
As part of our efforts to contain construction dust from infiltrating
the building, the construction crews have completed a temporary wall and door
at the top of the staircase to the roof and have also tarped over the two
skylights. Our project manager has met with our air conditioning service
company, and learned that our system does not intake outside air, but
re-circulates interior air. The only air conditioning equipment on the roof is
a cooling tower, which circulates water through the building in enclosed pipes.
Even though the interior air has been testing well, this morning our air
conditioning service company inspected and replaced the filters to the air
handling unit, which is located on the second floor. This should put to rest
any further concerns about the air conditioning system.
We have been ventilating the third and fourth floor by opening the
windows for four hours in the evening, and then resealing the window interiors
before construction work begins the next day. Air testing since these
procedures have been followed already shows a marked improvement in carbon
dioxide levels. For those rooms that don’t have air conditioners, we
expect that windows will be able to be opened during the day.
In the near term, to minimize the time our scaffolding remains erected
over our neighbor’s property, the contractor plans to remove the parapet
wall on the east side of the building on Friday, May 30 and on Monday and Tuesday,
June 2 and 3. This may create moderate noise and dust on those days and we will
do what we can to contain the dust and noise to the roof area. Also during the
week of June 2 the mobilization (scaffold erection) for the library will take
place on Thursday, not Friday of that week. Finally, on June 16 through June 20
work on the lightwell will require scaffolding to be erected in the Ballroom,
which will take it out of use during that time. The After School program will
make other arrangements on those days.
Thank you for your consideration.
|